10th Avenue Construction & Building Closures Notice
10th Avenue Construction & Building Closures Notice
The city has notified us of ongoing closures along portions of 10th Avenue starting now throughout the end of the school year. Families and visitors are encouraged to plan ahead, allow extra travel time, and use alternate routes as needed.
As we prepare for a busy summer of renovations, please be aware that Antigo High School will be closed to all staff and visitors from June 1 through August 9. During this time, there will be no access to the building due to construction and safety requirements.
Summer school programming and weightlifting activities will be relocated to the middle school.
We appreciate your flexibility and understanding as we work to improve our facilities. Additional updates will be shared as needed.
In November 2024, our community approved a $54 million capital referendum for the Unified School District of Antigo. A portion of the funds will be used to build a brand-new elementary school building, John H. Bradley Elementary School.
Construction on John H. Bradley Elementary began in August 2025, with an anticipated completion date of December 1, 2026. This page will be updated regularly as work progresses. Please check back for the most recent updates!
MAY 2026
Significant progress in Area A continues with woodgrain longboard installation, concrete floor pouring, and painting in the gym. In the kitchen, quarry tile installation has been completed.
In Area A, stainless steel equipment and quarry tile are being installed in the kitchen. Additionally, the overhead door installation has been completed in the kitchen’s receiving area. Masonry work continues in Area B.
In progress masonry installation in exterior staircase.
Ceiling grid, window, and metal panel installation has begun in Area A. In Area B, concrete is being poured while load-bearing walls are being constructed.
Exterior of building under construction surrounded by snow.
Painting continues in the main entrance Area A, along with plywood installation in the truss area. The masonry veneer has been completed in south Area A and along the west side of the school. In Area B, steel decking was installed in the central hub.
The walk-in freezer and cooler have been installed in Area A South. Masonry walls are being constructed, and steel is being set in Area B. On the southwest side of the school, masonry stone and brick veneer installation is ongoing.
Work continues to progress in the main corridor, where wood trusses are fully installed and exterior wood sheathing is complete. In Southern Area A, finishing and painting are ongoing. Also in Area A, the installation of mechanical, electrical, and plumbing systems is underway.
Structural steel has been installed in the main corridor between the gymnasium and the library. Wood and cold-formed roof trusses will be installed in the coming weeks. Roofing work in the Commons is underway and expected to be completed soon. Most recently, masonry work has begun on the east wall of the library, with crews working under tented enclosures due to the cold weather.
Wood-timber trusses are being installed in the main corridor, with cold-formed roof trusses to follow. An air and vapor barrier is being applied to the gym building in preparation for the masonry veneer installation. Inside the building, the first round of painting is underway in mechanical areas to coat the walls prior to equipment installation.
Steel joists and decking are being installed for the Commons area, giving shape to one of the school’s central gathering spaces. Masonry work is also advancing steadily, and the elevator shaft has been fully completed. In Area A, concrete pads for mechanical equipment have been poured, and roofing installation is underway in that section of the structure.
The final concrete foundation walls are nearly complete, and the slab on grade in the commons area is scheduled to be poured this week. In the gym, steel joists and acoustical decking have been installed, and roof blocking is underway in preparation for roof installation.